At present I am working as a Construction Project Manager since November,1918 to supervising and managing the High rising Towers ,of Madina Mall and Residency project ,Islamabad./p
As a project manager,I was responsible for the following:
To Collaborate with engineers, architect to determine and define scope of work and deliverables. Obtain necessary permit, approvals and other regulatory prerequisites./p
p· Plan Construction schedule & intermediate phases to ensure timely completion of projects./p
p· Hire contractors & other staff and Provide direction over contracts & manage relationship./p
p· Predict resources (manpower, equipment , materials) & monitor stocks to handles inadequacies./p
p· Oversee the work of Surveyors, supervisor ,mechanics ,labor and guide them if needed./p
p· Manage progress meeting and Issue updates and reports regarding cost and timelines./p
p· Ensure work is executed in accordance with drawings and technical specifications./p
p· Ensure adherence to all health and safety standard and repot issues./p
p .Evaluate the bills of Contractors and preparing of payment certificates for owner./p
pstrongPROJECTS COMPLETED/strong/p
pFrom July 1917 to october 1918 work as Project manager in Home Lanad Builder for construction of Residential Buildings in Bahria Town rawalpindi ./p
pFrom May 1915 to June 1917 work as a Project Manager with Emara CContracting Dubai. for construction of 4 Star hotel and high rising Towers ( G + 5P + 12)in Dubai ,Barsha./p
pFrom September 1912 to April 1915 work as Project manager for construction of Villas in Al Wadi Al abyad contracting Dubai./p
pFrom January 1909 to July 1912 work with Construction Tech Ajman as a Projec Manager /Project Engineer for construction of High Rising 12 towers( G+5+31 Typical) Ajman Pearl Project,Ramada Hotel ,Benquet Hall and commercial Towers ./p
/div
At present working in Salman Enterprises for Management and supervision of Madina Mall and Residency Project High rising Towers,• Managing and implementing the preconstruction, construction, testing , commissioning, project closeout phases with an emphasis on establishing and supporting the project controls, completing projects in a timely and cost-effective manner.
• Steady Drawings, Collaborate with engineers, architect to determine and define scope of work and deliverables. Obtain necessary permit, and other regulatory prerequisites.
• Hire contractors & staff and Provide direction over contracts & manage relationship. Liaise and coordinate with third party contractors in order to ensure that shop drawings (Civil + MEP) and programs of work are properly communicated
• Predict resources (manpower, equipment , materials) & monitor stocks to handles inadequacies. Review the contractor’s bill for payment coordination with Q.S.
• Oversee the work of Surveyors, supervisor ,mechanics ,labor and guide them if needed.
• Manage progress meeting and Issue updates and reports regarding cost and timelines.
• Ensure work is executed in accordance with drawings and technical specifications.
• Ensure adherence to all health and safety standard and repot issues.
• Work typically on multiple projects simultaneously and able to work in a fast‐paced, multi‐task environment, balancing competing priorities and multiple project assignments.
• Accurate and thorough analyses of costs and market conditions
Projects Supervised /Completed: Period (Dec,2010 to 2021)From November 2018 to Date: Senior Contruction Manager Madina mall & Residency Project (G+2B+Mall+13 Typical) 9 Towers
From November,2017 to October 2018 - Senior Construction Manager ,Construction of GulbergTrade Center and Villas Projects Home Land Builders Islamabad.
From May,2015 to Oct,2017: As Project Manager for Construction of 4 Star hotel , Emara Contracting LLC.Dubai.
From July 2012 toApr ,2015 : Construction of infrastructure and life style villas projects,Wadi Al abjad Contractin Dubai.
Dec,2010 to June ,2012 As Project Manager:Construction of High rise Towers upto 40 storey , Banquet hall .Position: Construction Manager ( Period from 2007 to ,2010 )
Project s Supervised /Completed: (Period from 2007 to 2010)
From Jan 2009 to Dec ,2010.Construction of High rise towers (G+2+17 to G+7+33 typical), Residential buildings, ware houses.
From Jun,2008 to Jan,2009: Construction of Commercial and residential high Rising Towers G+4 to G+50 With Al KANZ Contracting LLC.UAE.
From July 2007 to May ,2008 : Construction of commercial buildings and infrastructure of villa projects with Al Qantra General Contracting Ajman ,UAE
From Jan 2001 to Oct 2006 Client: Pakistan, WAPDA -Mangla Dam, Project-
Excavation/Desilting of power channels Rasul power station using Heavy machinery.
Routine maintenance of Mangla Dam earth fill Dam and desilting of seepage drains.
Repair and maintenance of machinery to keep ready for any emergency at Dam Area
Oversee store and procurement of building materials, mechanical parts for equipment.
Time From: Feb:1994 to Dec: 2001 Client :Pakistan- WAPDA(G B H P -Tarbella).
Construction of Infrastructure like Water supply and Sewerage pipe line & system.
Construction and maintenance of residential colonies & services of 506 houses.
Re surfacing of Faqeerabad roads and infra structures storm water ,cause ways
Re construction of internal roads in Resettlement colony comprising 416 houses.
Time Period: Jan 1991- Jan1994. Client: Pakistan- WAPDA (SCARP R.Y.Khan).
Construction of Bridges and other structures for surface drain ( World Bank aided projects): Construction of Abbasia Link Canal 5000 cusecs discharge earth work/bridges..
construction of residential buildings, Laying of trunk sewer( 66 “ ,48” and 30” dia pipe).
Construction of Pre stressed concrete plant &Precast of R C C concrete poles@Sargohda..